Airfield Upgrade Project At VC Bird International Enters Crucial Third Phase

1 March 2026 - 13:04

Airfield Upgrade Project At VC Bird International Enters Crucial Third Phase

1 March 2026 - 13:04

ST. GEORGE, 1st March, 2026…The multi-million dollar upgrade to the airfield of the VC Bird International Airport is recording steady progress and the project has now seamlessly moved into another critical phase. The third phase of the project is now underway and like the previous phases will see the completion of important airside enhancements designed to align the VC Bird International with global and modern aviation standards. Members of the public and nearby communities are asked to note that the work in this third phase will take place during the night time hours, starting at 8pm and ending at 8am the following day from Monday until Saturday each week until 15 April, the anticipated date of completion. This phase of the project will involve reconstructing the asphalt section of the displaced Runway 07 and a new Runway End Safety Area (RESA). The RESA is a crucial safety provision that reduces risk if an aircraft overshoots or veers off the runway. Also in this phase, the construction and technical teams will install new approach lights, runway edge lights, and turnpad edge lights across the airfield. These upgrades will improve visibility and enhance overall operational efficiency for aircraft during takeoff and landing at the VC Bird International Airport.

PRESS RELEASE

 

ST. GEORGE, 1st March, 2026…The multi-million dollar upgrade to the airfield of the VC Bird International Airport is recording steady progress and the project has now seamlessly moved into another critical phase.

The third phase of the project is now underway and like the previous phases will see the completion of important airside enhancements designed to align the VC Bird International with global and modern aviation standards.

Members of the public and nearby communities are asked to note that the work in this third phase will take place during the night time hours, starting at 8pm and ending at 8am the following day from Monday until Saturday each week until 15 April, the anticipated date of completion.

This phase of the project will involve reconstructing the asphalt section of the displaced Runway 07 and a new Runway End Safety Area (RESA). The RESA is a crucial safety provision that reduces risk if an aircraft overshoots or veers off the runway.

Also in this phase, the construction and technical teams will install new approach lights, runway edge lights, and turnpad edge lights across the airfield. These upgrades will improve visibility and enhance overall operational efficiency for aircraft during takeoff and landing at the VC Bird International Airport.

“We are very pleased with the progress of the work so far. At the end of the project, the VC Bird International Airport will be able to proudly boast a modern airfield that will only reinforce its status as a standard bearer of aviation in the Caribbean,” stated Operations Manager Rex Daly.

For inquiries related to the Airfield Rehabilitation Project, kindly contact our Operations Department office at 484-2300.

About The Author

Editorial Staff

The Editorial Staff refers to all reporters employed by Antigua.news. When an article is not an original creation of Antigua.news—such as when it is based on a press release, other media articles, letters to the editor, or court decisions—one of our staff members is responsible for overseeing its publication. Contact: [email protected]

2 Comments

  1. Good work

    Reply
  2. This is how development should happen phased, structured, and aligned with international standards.

    Reply

Submit a Comment

Your email address will not be published. Required fields are marked *

Antigua News - Breaking stories that captivate
Privacy summary

This website uses cookies so that we can provide you with the best possible user experience. Cookie information is stored in your browser and performs functions such as recognising you when you return to our site or helping our team understand which parts of the site you find most interesting and useful. More information in Privacy Policy