Valley Road Sidewalk Project Continues

You can now listen to Antigua News articles!

Photo Credit GIS

Work is progressing on the construction of 1.2miles (6,200ft/ 1,915m) of sidewalks from Ebenezer to Jolly Harbour (Valley Road).
Approximately 25% of the sidewalks have already been completed.
The sidewalks are 1.2m/ 4ft wide though the full width may not be achieved in built up area because of property fences, roadside drains, utility poles etc.
The project aims to improve property access, vehicular and pedestrian traffic.
Project Contractor C O Williams has pledged to take the necessary precautions to minimize the impact on pedestrians when the new school year commences in September.

3 Comments

  1. Janice

    The sidewalks was a good idea,but they should’ve started it sooner

    Reply
  2. tammy

    25% is far from done,I hope it wouldn’t be to much of an issue when school opens

    Reply
  3. Jerald

    They should start putting poles,for when it gets dark

    Reply

Submit a Comment

Your email address will not be published. Required fields are marked *

Antigua News ! - Breaking stories that captivate
Privacy summary

This website uses cookies so that we can provide you with the best possible user experience. Cookie information is stored in your browser and performs functions such as recognising you when you return to our site or helping our team understand which parts of the site you find most interesting and useful. More information in Privacy Policy