Major Milestone Reached in US$50 Million Upgrade of Airfield at the VC Bird International

20 February 2026 - 08:08

Major Milestone Reached in US$50 Million Upgrade of Airfield at the VC Bird International

20 February 2026 - 08:08
Major Milestone Reached in US$50 Million Upgrade of Airfield at the VC Bird International

Major Milestone Reached in US$50 Million Upgrade of Airfield at the VC Bird International

The first phase of the Airfield Rehabilitation Project at the VC Bird International Airport has now been completed. It represents a significant milestone in the US$50 million upgrade, one of Antigua and Barbuda’s largest and most transformative infrastructural projects in recent history. 

With work on the first phase completed, the full operational length of the runway is now once again being utilised to take international flights. The various upgrades also ensure an increased level of safety performance and compliance with international civil aviation regulations. 

Minister of Tourism, Civil Aviation, Transportation and Investment, Charles Fernandez, who was taken on tour of the project this week, expressed his full satisfaction with the level and quality of work. He noted that it clearly signals that Antigua and Barbuda is on the right track as a leader in the aviation industry in the Caribbean.

Fernandez stated, “The successful completion of the first phase of the Runway Rehabilitation Project on time and within budget is a testament to the strategic collaboration between our designers, contractors, operational teams, and all key stakeholders.” 

“Importantly, this critical infrastructure upgrade has progressed without disrupting airport operations, even during one of our busiest airlift seasons. This project strengthens safety, enhances resilience, and ensures that V.C. Bird International Airport continues to operate as one of the most dynamic and forward-moving aviation gateways in the region,” the Minister added.

  • Construction of a new, expanded Runway 25 turnpad (approximately 7,250 m ²), designed using the Airbus A350-1000 as the reference aircraft
  • Installation of new runway end lights, runway edge lighting, and turnpad edge lighting 
  • Establishment of a dedicated blast pad 
  • Implementation of a compliant Runway End Safety Area (RESA) 
  • Construction of a perimeter service road along the aerodrome boundary 
  • Addition of ICAO-recommended surface markings, including blast pad chevrons and transverse striping on turn pad shoulders, enhancing conspicuity and improving pilot situational awareness 

According to Joseph, one of the most pivotal improvements that the first phase achieved was the repurposing of Runway 25 to accommodate larger aircraft. 

“While aircraft such as the Boeing 777-200 were able to operate safely, the redesigned infrastructure now aligns with both current compliance expectations and future wide body operational requirements,” Daly further explained. 

The Runway End Safety Area (RESA) is another significant development. Not unlike many airports in the Caribbean, the VC Bird International sits close to the coastline so space for expansion has always been limited. To create a proper Runway End Safety Area(RESA), about 130 metres of runway pavement was removed during the project and operational distances adjusted. 

“While this slightly shortens the runway, it greatly improves safety by providing more protection at the runway’s end and brings the airport fully in line with international aviation safety standards,” Daly added. 

Work on the next phases of the airfield upgrade continues on schedule. Phase 2 is expected to conclude by Saturday night, paving the way for Phase 3 to begin on Monday night. This next stage will involve construction of the alternate turn pad and the temporary closure of the existing Runway 07 threshold to facilitate reconstruction works.

At the same time, Phase 5 will proceed alongside Phases 3 and 6, focusing on paving the Runway 07-25 overlay to enhance overall runway performance and safety. The project remains on track with substantial completion targeted for 6 July 2026 and full completion scheduled for 6 September 2026. 

About The Author

Editorial Staff

The Editorial Staff refers to all reporters employed by Antigua.news. When an article is not an original creation of Antigua.news—such as when it is based on a press release, other media articles, letters to the editor, or court decisions—one of our staff members is responsible for overseeing its publication. Contact: [email protected]

4 Comments

  1. With all that money pumped in that project I better see the difference and improvement

    Reply
  2. Big up to the team! This is what progress looks like. Safety first and we still operating during peak season? Respect.

    Reply
  3. On time AND within budget? That’s something we don’t hear every day. Well done to all involved 👏🏽

    Reply
  4. great. now let the upgrade begin

    Reply

Submit a Comment

Your email address will not be published. Required fields are marked *

Antigua News - Breaking stories that captivate
Privacy summary

This website uses cookies so that we can provide you with the best possible user experience. Cookie information is stored in your browser and performs functions such as recognising you when you return to our site or helping our team understand which parts of the site you find most interesting and useful. More information in Privacy Policy